Select Type of Project Here
Selecting a Location
1.) If your adding to an existing structure, it will be necessary to
drill and dowel
into the existing foundation. Call your electric or gas company and find out who to call to have
your property checked for underground utilities if you don't know already.
2.) Refer to these illustrations
for how to setup a batter board to level this type of foundation. Local codes will vary. Some areas
will require a deeper footing due to frost lines. For those, we will add a section for basements and
crawl space later. You will find these type foundations more in the southern regions where there are
very little to no frost line.
Forms
3.) Once you've setup the batter board and the string line is square, drive 2x4 stakes every 3' feet
around the outside perimeter using the string as a guide. On areas where the string is over 18" from
the ground, space your stakes every two feet and hold a level next to start the stake to
help ensure the bottom of the foundation be plumb with the top.
4.) Start at the string and install the first form board using the string as a height gauge.
Tip: strings tend to sag in the center, allowing for this will help make your concrete strait.
Fasten with #10 duplex head nails. If more than one row of forms are required, stagger each row for
more strength. Install all forms and secure to each stake and at the corners. It may be necessary
to rip the bottom form for a snug fit to the ground.
5.) Refer to these illustrations
to get an idea of the many concrete slab configurations. Dig your beams according to your plan and the
specifications of your local codes. Any plumbing or electrical needing to be installed under the slab
should be done after beams are dug.
Specifications
6.) Using a string along the top of the form, remove any earth within 6" then backfill with sand so
your concrete is a minimum of 4" thick.
7.) Slab foundation require a vapor barrier to be installed under the concrete. Use a suitable 6 mill
plastic sheathing.
Reinforcement
8.) Measure 12" from a corner and drive two #3 rebar stakes cut 6" longer than the height of the
form measuring from the bottom of the trench. Drive the first at 2-1/2" away from the outside form
and the second at 7-1/2". Repeat this every four feet on each side and down every beam starting and
ending 12" from a corner or the end of the beam. Drive stakes 1-1/2" below top of form, 3-1/2" where
there is a brick ledge.
9.) Using 20' lengths,
bend a piece of #5 rebar about 4' from the end at a 90 degree angle. Set this piece in a corner
and lay between the outside rebar stakes and the form, attach it to the steaks with wire ties about
3" off the bottom of the trench. Bend another #5 rebar at 4' and install in the same corner directly
above the first but because the ends of the rebar should be staggered and not break one over the other,
install with the 4' section facing the opposite direction and at 3" from the top, 4" if there is a brick
ledge.
10.) Bend two more pieces, this time at 8', and install at the same height as the first two bars accept
these are installed on the inner stakes. Be careful not to break the ends one over the other. Install
rebar around the perimeter overlapping bars a minimum of 40 diameters, or 25" for #5 (5/8") rebar. Steel
should be within 3" of the bottom and top. If rows are farther than 20" apart install another inside
and outside row of #5 steel in the center. Any brick ledge needed may be installed now.
Bracing
11.) On areas where the form is more than 6" above the ground, drive a 2x4 stake 2 to 4' out from each
form stake, drive till it is very firm and deep into the soil.
12.) On areas where the form is 18" or more above the ground, following
this example, measure for a
2x4 brace to lay directly on the ground between this new stake and the form stake. Next, measure for
a 2x4 to set on top of the first brace and extend to the top of the same form stake. Nail securely
with #16 nails.
Pouring
13.) I will explain what I think is the easiest way to do this. First you will need a temporary
center form which will be removed after you pour. This form will be used to screed(see Pouring
below) the concrete. Setup a string from one end to the other to set the height of the center
form. Drive some short 1x2 stakes every 3' until the top of the stake is just below the string
lay a 1x4 next to the stakes and using the string as a height gauge, fasten the 1x4 to the stakes.
Tip: strings tend to sag in the center, allowing for this will help keep your slabs strait.
14.) A pump truck is the best tool for pouring large slabs. Smaller ones can be easily poured with
just a truck. If access is not possible for a truck, several wheel borrows and a lot of help is an
option. Other options include machines such as concrete buggies or a tractors with a bucket. However
you decide to do it, dump some concrete near the center between your forms about 4' from the end.
Using rakes or tools called comealongs, move the concrete till it is evenly distributed throughout
from one form to the other. Use a long 2x4 or 2x6 called a screed and drag across the top of the forms
to make the concrete even with the top. Pour more concrete as needed and push into the low areas or
drag concrete out of the high areas as you drag the screed. After pouring an area you may no longer
need the center form, so pull it out of the concrete as you go. For example, if your 1x4 form is in
12' lengths, pour about 13 to 14' all the way across the slab, then pull up that 12' section of form.
You may also want to toss some concrete into the divot left by the form while you can still reach it.
15.) When you reach the end of the pour, use a tool called a bull float, which is a large adjustable
metal trowel about 3 to 4 feet long with a multi sectional handle. Assemble the float and starting
back at the beginning of the pour.
16.) Run the float back and forth in one area till all the pits have disappeared. Then move down a
few feet and start again. Have someone following behind you and install the foundation bolts.
Locate bolts 18" from the corners and every 6' around perimeter. Set bolts back from form or brick
ledge 1-3/4" for 2x4 walls or 2-3/4" for 2x6 walls. Do about 8' on each side of the foundation at
a time with the float so concrete doesn't get away from you. Do this till you reach the end of the
pour. Water can be sprinkled on the surface if necessary to help remove the pits. Once the surface
has all the pits and imperfections filled by the bull float your ready to move on.
Finishing
17.) Once the surface is firm enough to support a person standing on it, set a troweling machine on
top and try to run it. If the blades turn without digging into the surface, start troweling, two machines
would be better than one. Have one or two persons hand trowel around the plumbing pipes and foundation bolts
ahead of the machine. To help in the removal of forms, you can lightly run an edger around the perimeter.
Keep running the troweling machine till it is no longer needed. Water can be sprinkled lightly to help take
out ridges and imperfections if the concrete drys to fast.
|